"While you're here...": how to handle extra work with change orders

What to do when a customer asks for one more thing halfway through the job: spot extra work, price it on the spot, get a yes in writing before you start, and bill it so nobody is surprised at the end.

By the SmoothFlo team · Updated November 18, 2026 · 7 min read


You're two days into repainting a main floor. The homeowner walks over and says, "While you're here, could you do the powder room too?" It's a small room. The crew is already set up. Saying "sure" feels like good service.

The trouble shows up a week later, when the final bill is $550 higher than the quote and the customer doesn't remember agreeing to that. Or you never bill it at all, and the job you priced carefully quietly loses its profit. A change order fixes both, and it takes about five minutes.

What a change order is

A change order is a short note that changes a quote the customer already signed. It says what's being added or taken out, what it does to the price, and has the customer's OK on it. You send it before you do the extra work, not after.

It doesn't need to be formal or long. A few lines on the customer's phone are enough. What matters is that it's written down, it has a price, and they said yes.

What counts as extra work

Anything that isn't on the quote they signed. Most of it falls into a few groups:

  • More of the job: another room, the stairwell, the garage door, a second fence gate.
  • Upgrades: a better paint line, a different sheen, an accent wall in a second colour.
  • Changes of mind: a new colour after the first coat is already on.
  • Surprises found once work starts: soft trim, water damage behind old wallpaper, far more drywall repair than anyone could see at the visit.
  • Less work: the customer drops a room or decides to do the closets themselves.

This is much easier when your quote says clearly what's included, and what isn't. If every line lists its prep, coats and cleanup, there's no debate later about whether the closet was part of the bedroom. See how to write an estimate customers say yes to.

Why "I'll just add it to the bill" goes wrong

  • People remember prices differently. You said "around four hundred". They heard "a small thing".
  • The other person who signs the cheque wasn't there when you agreed.
  • The end of the job is the worst time to talk about money. Everyone just wants to be done.
  • Small favours add up, and they come straight off your profit.

Here's what three "small" extras on one painting job can really cost, using the same kind of rates you'd quote with:

ExtraPainter timePaint and suppliesFair price to the customer
Powder room walls and ceiling3 hours$40$280
Accent wall in a second colour1.5 hours$35$150
Patching 8 more dents and nail pops1.5 hours$15$120
Total6 hours$90$550

That's most of a day's work. Do it for free on every job and you've given away a few weeks of wages by the end of the season.

The rule: price it, get a yes, then do it

  1. 1Say it out loud, kindly. "Happy to do that. It isn't part of the quote, so let me price it for you." Most customers expect this and respect it.
  2. 2Price it from the same rates as the original quote. If walls were $1.85 a square foot on the quote, they're $1.85 in the powder room too. Same rates means no haggling.
  3. 3Write it down: what you'll do, the price, and whether it adds time to the job ("adds half a day, we'll still finish Friday").
  4. 4Get a written yes before you start. A signature is best. A text back saying "yes, go ahead" is far better than a nod in the hallway.
  5. 5Then do the work.

Speed matters here. If the price takes until the weekend, the crew either waits around or does the work anyway without an OK. Aim to send the change order before you leave the house that day, while the customer is still standing there thinking about it.

When you find a surprise behind the wall

Hidden problems are the hardest change orders, because the customer didn't ask for them. Don't cover the problem up, and don't quietly fix it for free hoping they'll notice. Instead:

  1. 1Stop work on that spot and take a few clear photos.
  2. 2Show the customer in person if they're home, or send the photos with a short note if they're not.
  3. 3Give them two or three options with a price for each: fix it properly, a quicker patch, or leave it and paint around it.
  4. 4Carry on with the rest of the job while they decide.

When the customer says no

That's fine. Note it and carry on with the job they signed for. A declined change order is still useful: it shows they were offered the work and chose not to, so nobody asks at the end why the powder room wasn't painted. It's also a ready-made small job to bring up again next season.

When the price goes down

Send a change order when work comes off the job too. If the customer decides to paint the closets themselves, put the lower price in writing. It keeps the final bill matching what was agreed, and customers remember the contractor who took money off without being asked.

Bill it so nothing is a surprise

On the final invoice, show the original quote first, then each change order on its own line with its price. The customer sees exactly what came from where. Folding everything into one bigger total is how a fair bill starts to look padded.

Invoice lineAmount
Main floor repaint (signed quote)$3,589.60
Change order #1: powder room walls and ceiling$280.00
Change order #2: accent wall, second colour$150.00
Price before tax$4,019.60

Change orders in SmoothFlo

Once a customer signs an estimate in SmoothFlo, it locks, so nobody changes a signed price by accident. When the job changes, you unlock it, make the changes in the same estimate builder you quoted with, and send them for signature.

  • SmoothFlo works out what changed since the customer signed and lists each change, with the total they agreed to and the new total.
  • Send it by text or email. The customer opens it on their phone, can untick any change they'd rather skip (the new total updates as they go), and signs with their name. They can also decline it and leave a note.
  • Until they approve, their link still shows the estimate they signed, so nothing changes behind their back.
  • You can be emailed when they approve or decline, so you know whether to start the extra work.
  • Approved change orders go onto the job's invoice as their own lines, under the original estimate.
  • Change orders come with every plan, including Starter.
A painting estimate open on a phone, with each room, what's included and the price
Customers read and sign on their phones, so a change order can go out from the job site and come back signed before lunch.

Quick checklist

  1. 1Your quote says what's included and that surprise repairs are priced separately.
  2. 2Any change, big or small, gets a price before the work starts.
  3. 3Same rates as the original quote.
  4. 4A written yes: a signature, or at least a text.
  5. 5Work coming off the job gets a change order too.
  6. 6Each change order on its own line on the final invoice.

Questions contractors ask

What is a change order for a contractor?

A short written note that changes a quote the customer already signed. It lists what's being added or removed, the new price, and the customer's approval, and it's agreed before the extra work is done.

How do I charge a customer for extra work?

Price it from the same rates as your original quote, send it in writing, and get their OK before you start. Then put it on the final invoice as its own line, under the original quote.

What if the customer won't approve the change order?

Don't do the extra work. Finish the job they signed for, and offer the extra as its own small job later.

Do small changes really need a change order?

If it changes the price or the time on the job, yes, even if it's just a text. If you decide to do something for free, say so in writing too ("no charge for the closet door"), so it's a favour, not an expectation.